Sunday, April 25, 2010

Moving to the inside



With most of the framing complete, work has continued on the inside- The photo is taken from the living room and shows the kitchen/dining/entry area (see sketch from February 4 2010). Electrical and plumbing subs started to put their part of the work in place and next week, the built up roof over the bathrooms & kitchen will go up. With more rain in the forecast, it is about time to get the place waterproofed so that the other interior trades such as the mechanical sub can get started as well. We're about four to six weeks behind the initial schedule at this point.